Heat Recovery Steam Generator

Kallo, Belgium
Client: IDO EET / Borealis Kallo NV
Year of Completion: 2017
1 x HRSG
  • 95 t/h
  • 43 bar (a)
  • 410 °C
  • horizontal
  • single pressure
  • process waste heat
Scope: basic and detail design only



Dubal, United Arab Emirates
Client: Dubai Aluminum
Year of Completion: 2015 - 2016
5 x HRSG
  • 228 t/h
  • 20 bar(a) 
  • 215 °C
  • vertical
  • single pressure with integrated de-aerator
  • brown field project with existing plant interfaces
Gas turbine:  9 BE



Ambarli, Turkey
Client: EP International BV
Year of Start-up: 2012
2 x HRSG
  •  281 / 47 / 29 t/h
  •  112 / 31 / 4 bar(a)
  •  530 / 524 / 194 °C
  • vertical
  • triple pressure with reheat and integrated de-aerator
  • „dry run“ concept
Gas turbine:  SGT5 – 4000F



Vologda, Russia
Client: Intertechelektro / TGK-2
Year of Start-up:  2012
1 x HRSG
  • 108 / 21 t/h
  • 93 / 6 bar(a)
  • 545 / 227 °C
  • horizontal,
  • double pressure with integrated deaerator
Gas turbine: GE 6FA



Mellach, Austria
Client: Siemens Power Generation
Anlagentechnik GmbH
Year of Start-up: 2011
2 x HRSG
  • 266,6 / 300,6 / 40,5 t/h
  • 129,5 / 29,9 /  4,3 bar(a) 
  • 559,6 / 560 / 226 °C
  • horizontal
  • triple pressure with reheat
Gas turbine: SGT5 – 4000F



Perm, Russia
Client: Siemens Industrial
Turbomachinery AB
Year of Start-up: 2011
2 x HRSG
  • 59,9 t/h
  • 84,2 bar(a)      
  • 512 °C
  • vertical
  • single pressure with district heating circuit
Gas turbine: SGT800



Linz-Mitte 1B, Austria
Client: Kraftanlagen München
Year of Start-up: 2009
1 x HRSG
  • 109 / 20,5 t/h 
  • 94 / 6 bar(a) 
  • 543 / 205 °C
  • vertical
  • double pressure with district heating circuit
Gas turbine: 6FA



Balloki, Pakistan
Client: Orient Power Company (Pvt) Ltd.
Year of Start-up: 2008
2 x HRSG
  • 111 / 17 t/h
  • 93 / 5 bar(a)
  • 538 / 270 °C
  • horizontal
  • double pressure
Gas turbine: GE 6FA



Bucuresti Vest, Romania
Client: Vatech Hydro
Year of Start-up: 2007
1 x HRSG
  • 262 t/h
  • 102 bar(a)
  • 511 °C
  • horizontal
  • single pressure with DHW heater and supplementary firing (55 MWth)
Gas turbine: GE 9E



Rya Göteborg, Sweden
Client: Siemens Industrial Turbomachinery AB
Year of Start-up: 2006
3 x HRSG
  • 158,6 t/h 
  • 103,5 bar(a)    
  • 542 °C
  • horizontal with water cooled combustion chamber
  • single pressure with DH circuit and supplementary firing (78 MWth)
Gas turbine: SGT800

3